How to Quote Electrical Work (With a Worked Example)
How to quote electrical work in Australia: per-point pricing built line by line, a worked switchboard quote, and certificate and contract rules by state.
In this article
To quote electrical work, inspect the switchboard and cable runs first, then price each item based on labour time, materials, and your markup. Put work you can't see yet in a capped provisional sum, list what you haven't priced, and show testing, the compliance certificate, GST, the deposit and how long the price holds.
The layout is the easy part. The hard part is knowing what the switchboard, access, and cable runs will cost before you start. This guide is for Australian electricians quoting homes and small commercial jobs. It covers how to build a per-point price, a full worked quote for a switchboard upgrade and kitchen job, the certificate and contract rules in NSW, Victoria and Queensland, and the mistakes that cost you margin.
The numbers in the examples are illustrative. Use your own hourly rate, supplier prices and install times.
What should an electrical quote include?
- Your business name, ABN, and your electrical contractor licence or registration number
- The customer's name and the site address
- A scope written point by point: what's being installed, where, and the brand and model for major items
- Labour and materials, either as per-point prices or as separate lines
- Testing and your state's compliance certificate, as their own line
- Any provisional sums, with how the final amount will be worked out
- Exclusions: what you haven't priced
- The subtotal, GST and total
- The deposit and payment terms
- How variations are handled
- How long the quote is valid for
In NSW, your contractor licence number must appear on your stationery, including quotes. For what a tax invoice needs once the job's done, see our guide to tax invoice requirements.
Hourly, per-point or fixed price: which should you use?
| Method | Best for | Watch out for |
|---|---|---|
| Hourly (do and charge) | Fault-finding, small repairs, and jobs you can't scope until you start | The customer can't compare it with other quotes. Give an estimate of hours and state your minimum charge. |
| Per point | Power points, lights, fans and smoke alarms on a straightforward install | The price assumes normal access. Two-storey drops, slab floors and no roof space need a loading or a separate line. |
| Fixed price | Switchboard upgrades, dedicated circuits, kitchen and renovation packages | You carry the risk. Inspect first, and use a provisional sum for anything you can't see. |
Most residential quotes use all three: per-point prices, a fixed price for the switchboard and new circuits, and an hourly provisional sum for fault-finding.
Step 1: Inspect before you price
The switchboard tells you more about the job than the customer does. Check these before you put a number on anything.
- Switchboard condition and space. Ceramic fuses, no RCDs, no room for new circuit breakers, or any sign of heat damage can mean the board needs replacing before you add anything.
- RCD protection. Under AS/NZS 3000, altering a final subcircuit means that circuit needs RCD protection, and replacing a switchboard means every final subcircuit on it needs RCD protection. Price it in now rather than finding it on the day.
- Supply capacity. An induction cooktop, EV charger or ducted air conditioner adds a lot of load. Check the main switch rating and the consumer mains before you promise a new circuit.
- The meter panel. Older meter panels can contain asbestos. Don't drill or cut it. Exclude its removal, or price it separately with a licensed removalist.
- Access. Roof space height and insulation, two-storey drops, concrete slabs, and tiled walls all affect how long each point takes.
- Cable runs. Measure from the board to each new circuit. Long runs of heavy cable for a cooktop or sub-board add up quickly.
- Existing faults. Test the circuits you'll be working on. If something fails, tell the customer before you quote, not after you start.
- Smoke alarms. In Queensland, every home must have interconnected photoelectric smoke alarms by 1 January 2027. If you're in the house, check them and offer a price.
Write down what you found, and take photos of the board and the meter panel. Your notes become the scope and the exclusions, and they're your record if anything is disputed later.
Step 2: Build your per-point prices
A per-point price is your labour time at your hourly rate, plus materials at cost, plus your markup on the materials. Work it out once for each item you install often, keep the list, and update it when your supplier prices change.
| Item | Materials at cost | Materials + 20% markup | Labour at $110/hr | Point price |
|---|---|---|---|---|
| LED downlight, cut in and wired | $28.00 | $33.60 | 0.5 hr = $55.00 | $88.60, rounded to $89 |
| Double power point on an existing circuit | $30.00 | $36.00 | 1 hr = $110.00 | $146.00 |
A 20% markup on materials is not a 20% margin: it's 16.7%. If you're pricing to a target margin, check it with the markup vs margin calculator or read our guide to markup vs margin.
Labour time is where per-point prices usually go wrong. Time your own installs for a few weeks and use your real averages, not a number from someone else's price list. Then add a loading for the hard jobs: a second storey, a slab floor or a ceiling with no access.
Your hourly rate also has to cover more than wages. It needs to pay for the van, tools, insurance, licences, the time you spend quoting and doing admin, and the hours you can't bill.
Step 3: Split the quote into fixed, PC and provisional
| Type of line | What it's for | Example |
|---|---|---|
| Fixed price | Work you've seen and can price with confidence | A new switchboard, six downlights, three power points |
| PC allowance (prime cost) | Fittings the customer hasn't chosen yet | Pendant lights over the island, allowed at $150 each, supply only |
| Provisional sum | Work you can't fully see or measure until you start | Fault-finding and repairs to existing circuits found during testing |
Every provisional sum needs three things: why it's there, the amount allowed, and how the final figure will be worked out (for example, actual hours at your rate plus parts at cost plus your markup). Without those, a provisional sum reads like a blank cheque, and customers notice.
A worked example: switchboard upgrade and kitchen electrical
The customer is renovating the kitchen in a 1970s brick house in western Sydney. The switchboard still has ceramic fuses and no RCDs. They want six LED downlights in the living area, three new double power points in the kitchen, a circuit for an induction cooktop and new smoke alarms throughout.
All prices below are illustrative and exclude GST. They use a $110 hourly rate and a 20% markup on materials.
| # | Line | Qty | Price | Amount |
|---|---|---|---|---|
| 1 | Replace switchboard: new enclosure, main switch and RCBOs on every circuit | 1 | $1,880.00 | $1,880.00 |
| 2 | Supply and install LED downlights, living area | 6 | $89.00 | $534.00 |
| 3 | Supply and install double power points, kitchen | 3 | $146.00 | $438.00 |
| 4 | New circuit for induction cooktop: cable, isolator and RCBO, and connect the cooktop | 1 | $621.00 | $621.00 |
| 5 | Supply and install 240V interconnected photoelectric smoke alarms | 3 | $204.00 | $612.00 |
| 6 | Site setup, travel and clean-up | 1 | $120.00 | $120.00 |
| 7 | Testing and Certificate of Compliance for Electrical Work (CCEW) | 1 | $165.00 | $165.00 |
| 8 | Provisional sum: fault-finding and repairs to existing circuits | 1 | $440.00 | $440.00 |
| Subtotal | $4,810.00 | |||
| GST | $481.00 | |||
| Total | $5,291.00 |
Here's how the bigger lines were built. The switchboard is 7 hours of labour ($770) plus $925 of materials at cost ($1,110 with markup). The cooktop circuit is 3 hours ($330) plus $242.50 of materials ($291 with markup). The smoke alarms are 3 hours ($330) plus $235 of alarms and cable ($282 with markup). Testing and the certificate are 1.5 hours. The provisional sum allows 4 hours.
The total is over $5,000 including GST. In NSW, that means this quote needs to become a written contract before work starts. There's more on that in the contracts section below.
Payment terms on this quote
| Stage | Amount |
|---|---|
| Deposit on signing (10%) | $529.10 |
| Balance, due 7 days after completion, adjusted for the provisional sum | $4,761.90 |
| Total | $5,291.00 |
Exclusions on this quote
Exclusions. This quote does not include: patching, sanding or painting after cutting in; removal of asbestos from the meter panel or anywhere else; upgrading the consumer mains or the service from the street; metering or network fees charged by your retailer or distributor; supply of the induction cooktop; electrical work outside the kitchen and living area, other than the switchboard and smoke alarms; or work outside 7am to 4pm on weekdays. Any of this will be quoted as a written variation before it starts.
Quote terms worth adding
This quote is valid for 30 days. The provisional sum is an estimate: the final amount will be the actual hours at $110 an hour plus parts at cost plus 20%, shown on the invoice, and we'll check with you before going over the allowance. You must agree to variations in writing before work starts, except where work is needed to make the installation safe. Your Certificate of Compliance for Electrical Work will be lodged and emailed to you within 7 days of testing.
Certificates: what each state requires
Testing and the certificate take time, so put them on the quote as a line and price them. It also shows the customer you'll do the job properly, which is one thing they compare between quotes.
| State | Certificate | Who gets a copy | Deadline |
|---|---|---|---|
| NSW | Certificate of Compliance for Electrical Work (CCEW), lodged through the Building Commission NSW eCert portal | The customer for all electrical work, and the regulator and distributor for many jobs | No later than 7 days after the safety and compliance test |
| VIC | Certificate of Electrical Safety (COES), prescribed or non-prescribed | The customer and Energy Safe Victoria, plus the distributor for prescribed work | Prescribed: within 16 calendar days of completion. Non-prescribed: within one month |
| QLD | Certificate of testing and compliance (installation work) or certificate of testing and safety (equipment work) | The person the work was done for | As soon as possible after the work is completed |
In Victoria, prescribed work must also be inspected by a licensed electrical inspector. Prescribed work includes consumer mains and main switchboards, so a switchboard replacement there needs an inspection. Put the inspection on the quote as its own line.
Rules change, and other states and territories have their own. Check with your regulator: Building Commission NSW, Energy Safe Victoria or the Electrical Safety Office in Queensland.
Contracts and deposits for electrical work
| State | Licence | Written contract | Deposit |
|---|---|---|---|
| NSW | Electrical wiring work is specialist work, so you need a contractor licence, whatever the job's value | Required for residential work over $5,000 including GST. Work over $20,000 needs the large job contract | Maximum 10% |
| VIC | Licensed by Energy Safe Victoria. Work for customers must go through a Registered Electrical Contractor | A job that is only electrical work doesn't need a major domestic building contract. Put the accepted quote in writing anyway | The domestic building deposit caps don't apply to electrical-only jobs. Agree the deposit in writing |
| QLD | Electrical contractor licence from the Electrical Safety Office, not the QBCC | Get the quote accepted in writing. If the job also includes building work, check the QBCC contract rules | Agree it in writing. Check QBCC rules if the job includes building work |
A deposit does two jobs. It shows the customer is committed, and it covers the switchboard and materials you've ordered for them. Ask for it as part of accepting the quote, and say in writing what happens to it if the job is cancelled.
Estimating vs quoting: when you need a take-off
On a house, you quote from what you see on site. On a commercial fit-out or a new build, you often price from drawings instead: a take-off counts every point, cable run and board from the plans, and the estimate becomes a tender. That's a different job, and many contractors use estimating software or an outsourced estimator.
The method in this guide still applies to the quote you send at the end: price from real install times, split fixed work from provisional, list exclusions, and put testing and certification on the page.
Common electrical quoting mistakes
- Pricing points before looking at the switchboard. The board can change the price of the whole job.
- One per-point price for every house. Two-storey, slab and no-roof-space jobs take longer. Add a loading.
- Leaving out testing, the certificate or the inspection. It's real time, and in Victoria the inspection is a real cost.
- Forgetting RCDs on altered circuits. If you alter a circuit, it needs RCD protection. Quote for it.
- Fault-finding with no cap. Use a provisional sum with an allowance and a way to work out the final figure.
- A vague scope. "Kitchen electrical" invites an argument. Say how many points, where, and which models.
- No exclusions. Patching and painting after cutting in is the most common dispute. Write it down.
- Promising a new circuit without checking supply capacity. An induction cooktop or EV charger can need more than the main switch allows.
- Sending the quote days later. The customer is often getting several quotes. The first clear one has an advantage.
What happens after you send the quote?
Follow it up. Most quotes aren't declined; they're forgotten. A short message on day 2, day 7, and day 14 keeps yours top of mind. Our guide to how to follow up a quote has the messages to send.
When it's accepted, get the acceptance in writing, take the deposit and order the board and materials.
When the job changes on site, price the extra work and get it agreed before you do it. See how to charge for variations.
When the job's done, test it, lodge the certificate and send the invoice the same day.
If the invoice isn't paid, send a short reminder 1, 7, 14 and 28 days after the due date. Here's what to send when a customer won't pay.
How Korda Pro fits in
Korda Pro is quoting and invoicing software for Australian trade businesses that turns a voice note into a quote or invoice, then chases the customer until the job is paid.
On site, you send a WhatsApp voice note the way you'd explain the job to a mate: "Quote for the Nguyens in Blacktown: replace the switchboard, six downlights at $89, three double power points at $146, the cooktop circuit at $621, three smoke alarms, testing and the CCEW, and a $440 provisional sum for fault-finding. Exclude patching and painting." Korda Pro replies with the itemised quote, GST and total. You check it in the chat, and nothing goes to the customer until you choose Send.
- Korda Pro follows up open quotes by SMS and email on days 2, 7 and 14, and stops when the customer accepts.
- You can log extra work found on site as a variation with a voice note, so it reaches the invoice.
- The accepted quote becomes an invoice in the same chat, saved to Xero if you use Xero.
- Unpaid invoices get payment reminders 1, 7, 14 and 28 days after the due date.
Korda Pro doesn't do take-offs from plans, and it doesn't issue compliance certificates. Your certificate still goes through your state's system.
Electrical quote FAQs
How do you quote electrical work?
Inspect the switchboard, access and cable runs first. Price each item from labour time, materials and your markup, put anything you can't see in a capped provisional sum, and list your exclusions. Then add testing and the compliance certificate, GST, the deposit and an expiry date.
What should an electrician's quote include?
Your business name, ABN and licence number, the customer and site address, an itemised scope with brands and models for major items, labour and materials, testing and the certificate, any provisional sums, exclusions, GST and the total, the deposit and payment terms, how variations work, and how long the quote is valid.
Should electricians charge per point or by the hour?
Charge per point for straightforward items like lights and alarms, hourly for fault-finding and repairs, and a fixed price for switchboards and packages. Most residential quotes use a mix of all three.
How do you work out a per-point price?
Add your labour time at your hourly rate to your materials at cost plus your markup. For example, half an hour at $110 plus $28 of materials marked up 20% comes to $88.60. These figures are illustrative, so use your own rate, times and supplier prices.
Should the compliance certificate be on the quote?
Yes. Testing and certification take time, so price them as their own line. In NSW, the CCEW must be lodged within 7 days of testing. In Victoria, the Certificate of Electrical Safety is due within 16 days for prescribed work and one month for non-prescribed work. In Queensland, the certificate goes to the customer as soon as possible after the work.
Do I need a written contract for electrical work?
In NSW, yes, for residential work over $5,000 including GST. In Victoria, a job that is only electrical work doesn't need a major domestic building contract. In Queensland, the Electrical Safety Office licenses electrical work. Wherever you are, get the quote accepted in writing.
How much deposit can an electrician take?
In NSW, the maximum deposit for residential building work, including electrical wiring, is 10%. In Victoria, the domestic building deposit caps don't apply to electrical-only jobs. Wherever you work, agree the deposit in writing when the quote is accepted.
How long should an electrical quote be valid for?
Many electricians use 30 days. If switchboard or cable prices are moving, use a shorter period and put the date on the quote.
Can I quote electrical work from photos?
A photo-based ballpark is fine to check the customer's budget. Give a fixed price after you've seen the switchboard and the access.
The bottom line
A clear electrical quote wins the job, and the detail protects your margin. Look at the switchboard first, build your point prices from real install times, cap what you can't see, put the certificate on the quote, and send it while the customer still remembers you.