How to Quote a Bathroom Renovation (Line by Line)
A tradie's guide to quoting a bathroom renovation in Australia: a line-by-line quote layout, PC items, provisional sums, deposits by state and exclusions.
Paul Coleman · Co-founder, Korda Pro
In this article
To quote a bathroom renovation, inspect the room first, then price the job trade by trade: preliminaries, demolition, plumbing, electrical, carpentry, waterproofing, tiling, fit-off and finishing. Put every line in one of three buckets (fixed price, prime cost allowance or provisional sum), list what's excluded, and add GST, a deposit and a payment schedule that follow your state's building rules.
This guide is for Australian tradies and small renovation businesses who quote bathrooms themselves. You know how to price your work. This is about laying the quote out so the customer trusts it and nothing gets missed. It lays out a full quote for a family bathroom, line by line, then covers allowances, deposits, variations and what happens after you hit send.
This is general information, not legal advice. Building rules change and differ by state, so check with your regulator before you sign a contract.
What should a bathroom renovation quote include?
A bathroom quote should show the customer exactly what they’re paying for, and show you exactly what you've promised. At a minimum, it needs:
- Your business name, ABN, licence number and contact details
- The customer's name and the site address
- A quote number, the date and an expiry date
- The scope of work, broken into trades or stages
- Itemised prices, the subtotal, GST and the total
- PC allowances and provisional sums, clearly marked
- Exclusions
- The deposit and payment schedule
- Estimated start date and duration
- How variations work
- A place for the customer to accept
business.gov.au's guide to preparing quotes lists the same basics. Take it seriously: in Queensland, QBCC points out that once a quote is accepted, even verbally, it becomes a legally binding contract.
How much does a bathroom renovation cost?
Customers usually arrive with a number in their head from online cost guides, so it helps to know the going rate before the first call. Blue Sky Home Renovations, a bathroom renovation business on the NSW Mid North Coast and Northern Beaches of Sydney, publishes these ranges from its own completed projects:
| Type of job | Typical cost (Blue Sky) | What it covers |
|---|---|---|
| Cosmetic refresh | $8,000 to $15,000 | New vanity, tapware, toilet suite and paint. Tiles and plumbing layout stay as they are. |
| Mid-range renovation | $30,000 to $45,000 + GST | Full strip-out, new waterproofing, tiling, fixtures and fit-off, keeping the existing drain and waste positions. |
| Premium renovation | $45,000 to $80,000+ | Custom cabinetry, high-end fixtures and finishes, and layout or structural changes. |
Source: Blue Sky Home Renovations, How much does a bathroom renovation cost in NSW? Indicative ranges from their completed projects, with GST shown as they publish it. For a national benchmark, Blue Sky cites HIA figures that put the average Australian bathroom renovation at around $26,000.
Blue Sky's director, Martyn Wilson, on why a realistic number is the place to start:
From Blue Sky Home Renovations
“Having a realistic budget early makes it easier to plan a bathroom that suits your home and priorities. Understanding what’s involved helps you decide where to invest and choose a layout and finishes with confidence.”
What those numbers tell you as the person quoting:
- Size matters less than you'd think. A compact ensuite still needs the same licensed trades and the same sequence as a family bathroom, so labour doesn't drop in line with floor area.
- Layout and finishes move the price most. Relocating a toilet or shower waste, custom cabinetry and large-format or imported tiles are the biggest drivers. Keeping the existing drain and waste positions makes a real difference.
- Older homes carry more risk. Homes built before 1990 can hide water damage, termite damage, rotten framing or asbestos behind the walls. That's why the provisional sum in Step 3 matters.
- Plan the timeline, not just the price. Blue Sky puts a full renovation at three to five weeks on site, and six to ten weeks from first consultation to handover. Put an estimated start date and duration on every quote.
Use ranges like these on the first call to check the customer's budget is realistic, not as your price. The quote itself should come from a site inspection and your own costs.
Step 1: Inspect before you price
Almost every bathroom that blows its budget does it behind the tiles. Spend time on site and write down what you see and what you can’t.
- Measure everything: floor area, wall heights, the shower area, window and door sizes. You'll need square metres for tiling and waterproofing.
- Plumbing: where the waste and water points are now, and whether the layout is changing. Moving a toilet or shower waste costs more than a like-for-like change.
- Electrical: fans, lights, power points, heated towel rails, and whether the switchboard can handle the extra load.
- Floor and walls: bounce in the floor, soft spots, cracked tiles, water stains on the ceiling below or the room next door.
- Age of the house: older homes, especially those built before 1990, may have asbestos in wall sheeting or under the floor tiles. Price testing in, or exclude removal and say so.
- Access: stairs, parking, where the skip goes, and whether the family is living there during the job.
Take photos of everything. If you can't see something, such as the subfloor, don't guess. That's what a provisional sum is for (Step 3).
Step 2: Break the job into trades and stages
Quote the scope, not "the bathroom". A single line that says "Bathroom renovation" with one price invites arguments later, because neither side can point to what was included. Break it down in the order the job runs:
- Preliminaries and protection
- Demolition and disposal
- Plumbing (rough-in and fit-off)
- Electrical
- Carpentry and wall sheeting
- Waterproofing
- Tiling
- Installing fixtures
- Painting and final clean. If you subcontract the plumbing or electrical, still show them as separate lines, and say the price includes the licensed trade’s labour, materials, and compliance certificate. Plumbing, gasfitting and electrical work must be done by appropriately licensed trades.
Waterproofing deserves its own line every time. Say which areas are being waterproofed, the system, that it will meet the Australian Standard for wet areas (AS 3740), and that a waterproofing certificate is included. "Waterproof bathroom" on its own tells the customer nothing.
Step 3: Use the three-bucket quote
Every line on a bathroom quote should sit in one of three buckets. This is what stops the "but I thought that was included" conversation.
| Bucket | What it's for | Example |
|---|---|---|
| Fixed price | Work you can see, measure and price with confidence | Tiling labour for the measured walls and floor |
| PC allowance (prime cost) | Fixtures the customer hasn't chosen yet | Vanity and basin, until the customer chooses one |
| Provisional sum | Work you can't fully see or measure until the job starts | Repair of floor framing, if rot is found after demolition |
PC allowances cover items the customer picks later, like the vanity, tiles and tapware. If they choose something dearer or cheaper, the price moves by the difference. NSW explains prime cost items as items chosen after signing that can't be costed exactly before work begins. Make each allowance realistic for the finish the customer described, not low to make the total look good.
Provisional sums cover work you can't price until you open things up. Say why each one is there and how the final amount will be worked out. Don't use them to cover for a quote you haven't finished.
A worked example: laying out a family bathroom quote
The job (illustrative): a full strip-out of a small 1970s family bathroom. The bath comes out, a walk-in shower goes in, and the walls are tiled floor to ceiling. The customer hasn't chosen fixtures yet.
The example leaves the prices out, because those come from your own costs and rates. It shows the order the lines go in, which bucket each one sits in, and what to spell out so the customer can see exactly what's included.
| # | Line | Bucket | What to spell out |
|---|---|---|---|
| 1 | Preliminaries and protection | Fixed | Site setup, floor and access protection, dust screens, final clean |
| 2 | Demolition and disposal | Fixed | What comes out (bath, vanity, toilet, tiles, wall sheeting), skip bin and tip fees |
| 3 | Plumbing | Fixed | Disconnect, any waste being moved, rough-in, fit-off, testing and compliance certificate |
| 4 | Electrical | Fixed | Exhaust fan and where it's ducted, lights, power points, heated towel rail, certificate |
| 5 | Carpentry and wall sheeting | Fixed | Wet-area sheeting, noggins for fixtures, framing for any niche |
| 6 | Waterproofing | Fixed | Areas and heights covered, the system, AS 3740, waterproofing certificate |
| 7 | Tiling labour | Fixed | Square metres of walls and floor, niches, trims, adhesive and grout |
| 8 | Install fixtures and accessories | Fixed | Everything being fitted, including any customer-supplied items |
| 9 | Painting | Fixed | Ceiling, door and trims, and that painting stops at the bathroom |
| 10 | Tiles | PC allowance | Square metres allowed for (including waste) and the allowance per square metre |
| 11 | Vanity and basin | PC allowance | The allowance, and that it covers supply only |
| 12 | Toilet suite | PC allowance | The allowance |
| 13 | Tapware and shower set | PC allowance | The allowance and what it includes |
| 14 | Shower screen | PC allowance | The allowance and the screen type, for example frameless |
| 15 | Towel rail and accessories | PC allowance | The allowance and the items included |
| 16 | Floor framing or subfloor repair | Provisional sum | Why it's there (damage can't be seen until demolition) and how the final cost will be worked out |
Below the lines, show a subtotal for each bucket, then GST and the total. The customer can see at a glance how much of the price is fixed and how much depends on their choices or on what's found behind the tiles.
Payment schedule (NSW example)
| Stage | Share of contract price |
|---|---|
| Deposit, after the contract is signed and home building compensation cover is in place | 10% |
| Demolition, and plumbing and electrical rough-in, complete | 25% |
| Waterproofing certified and tiling complete | 35% |
| Practical completion | 30% |
| Total | 100% |
Tie each stage to work the customer can see is finished. In Victoria and Queensland, the deposit cap drops to 5% once the contract price reaches $20,000, which covers most full bathroom renovations. More on that below.
Exclusions on this quote
Exclusions. This quote does not include: asbestos testing or removal; structural engineering; replacement of main drains or sewer lines; switchboard upgrades; council or certifier fees; mould remediation; painting outside the bathroom; work to rooms other than the bathroom; or fixtures supplied by the customer, other than installation. Any of this work will be quoted as a written variation before it starts.
How a PC allowance changes the price
Say the customer chooses a vanity that costs $450 more than the allowance. The price goes up by that $450 difference, or $495 including GST. If they pick something cheaper, it comes down by the difference. Write that rule into your quote so it's agreed upfront, and show the calculation when it happens.
Quote terms worth adding
This quote is valid for 30 days. PC allowances and provisional sums are estimates: the contract price will be adjusted by the difference between each allowance and the actual cost, and the calculation will be shown in writing. Variations must be agreed in writing before work starts, except where urgent work is needed to make the site safe.
How much deposit can you take on a bathroom renovation?
Bathroom renovations are residential building work, so your state's rules decide when you need a written contract, how much deposit you can take and when you need insurance. The three biggest states:
| State | Written contract | Maximum deposit | Insurance before taking money |
|---|---|---|---|
| NSW | Over $5,000 including GST. Small job contract up to $20,000, large job contract above $20,000 (large jobs also have a five clear business day cooling-off period) | 10% | Home building compensation cover for contracts over $20,000, in place before any deposit |
| VIC | A major domestic building contract for most work over $10,000 | 10% under $20,000; 5% at $20,000 or more | Domestic building insurance policy and certificate before taking money for work over $16,000 |
| QLD | Written contract for work over $3,300 | 20% up to $3,300; 10% from $3,301 to $19,999; 5% at $20,000 or more | Check QBCC home warranty requirements for your job |
Sources: NSW Government, contracts; Consumer Affairs Victoria, deposits and payments; QBCC, deposits and progress payments. Checked October 2026.
In other states and territories, check with your building regulator before you send the contract. And check that you hold the right licence for the work and its value in your state.
How do you price each line?
Price each line the same way: materials + labour + subcontractors + your overheads + margin. A few things bathroom quotes often leave out:
- Waste on tiles. Order for cuts and breakages, especially with large-format or patterned tiles.
- Drying and curing time. Waterproofing has to cure before tiling. That's time on the program, even if no one's on site.
- Trade coordination. Gaps between the plumber, sparky and tiler cost you days. Allow for it.
- Site costs. Parking, travel, skip bins, tip fees and protection materials.
- Callbacks. A silicone joint or a sticking drawer after handover is part of the job. Budget for it.
- Your margin, not just your markup. A 30% markup is only a 23% margin. The markup vs margin guide shows why that matters on a big job.
What homeowners compare when they get three quotes
Most bathroom customers get two or three quotes. The cheapest number on the page doesn't always win. What they compare:
- Is it the same job? A quote with clear lines is easier to trust than a single figure.
- Are the allowances realistic? A low tile allowance makes a quote look cheaper until the customer goes shopping.
- Is waterproofing spelled out? Customers know leaks are the expensive failure.
- Who does the plumbing and electrical, and are they licensed?
- What's not included? Clear exclusions read as honesty, not as hidden costs.
- How quickly did they hear back? A clear quote the same week beats a vague one a fortnight later.
How to handle variations on a bathroom job
Something always changes. The customer wants a second niche, or you find rot under the floor. Get every change agreed in writing before you do the work: what's changing, the cost and any extra time.
Example: the customer asks for a second shower niche. You send a variation with the price and any extra time; they approve it by message, and only then do you frame it. In NSW, variations must be in writing and signed, with the cost calculation shown. In Queensland, QBCC says the variation must be given in writing within five business days of agreeing it, or before the work starts, whichever comes first.
Our guide on how to charge for variations covers the wording and the habits that stop you from doing extra work for free.
Common bathroom quoting mistakes
- Quoting from photos alone. Fine for a ballpark, risky for a fixed price.
- One lump sum. It hides your thinking and invites disputes.
- Allowances set low to win the job. The customer finds out at the showroom, and you look bad.
- No provisional sum for what you can't see. Then the rot comes out of your margin.
- Forgetting the certificates. Plumbing, electrical and waterproofing certificates are part of the job and the price.
- Taking a bigger deposit than your state allows, or taking it before insurance is in place.
- Sending the quote and never following up. See below.
What happens after you send the quote?
A bathroom quote takes hours to write. Losing it because you didn't follow up is the most expensive mistake on this list.
- Follow up on a schedule. The 2-7-14 rule checks in two, seven and 14 days after sending, then lets the quote expire cleanly.
- Once it's accepted, send the contract, put insurance in place where your state needs it, then invoice the deposit.
- Invoice each stage when it's done, not at the end of the month.
- If a stage invoice goes overdue, the reminders in Customer won't pay your invoice? Show what to send, and when.
How Korda Pro fits in
- Walk the bathroom, send a voice note with what you measured and saw, and Korda Pro writes the draft quote for you to check and send.
- It follows up the quote for you, so a big job doesn't go quiet because you were on the tools.
- When the customer asks for changes, variations are written up and approved in writing before you do the work.
- Stage invoices go straight into Xero, and payment reminders go out at 1, 7, 14 and 28 days overdue until you're paid.
If you'd rather keep it manual, a spreadsheet or your accounting software's quote template works too, as long as it follows the three-bucket structure above.
Bathroom renovation quote FAQs
How do you quote a bathroom renovation?
Inspect the room, measure it, and note anything you can't see. Then price the job trade by trade, put each line in a bucket (fixed price, PC allowance or provisional sum), list exclusions, and add GST, a deposit and a payment schedule that follow your state's rules.
What should a bathroom renovation quote include?
Your business details, ABN and licence number, the customer and site address, an itemised scope by trade, PC allowances and provisional sums, exclusions, GST and the total, the deposit and payment schedule, timing, how variations work, and an expiry date.
What are PC items on a bathroom quote?
Prime cost (PC) items are allowances for fixtures the customer hasn't chosen yet, such as the vanity, tiles or tapware. If they choose something dearer or cheaper, the price is adjusted by the difference.
What is a provisional sum?
A provisional sum is an allowance for work you can't fully price until the job starts, such as repairing floor framing that may be rotten under the tiles. The quote should say why it's there and how the final amount will be worked out.
How much deposit can I ask for on a bathroom renovation?
It depends on your state and the contract price. In NSW the maximum is 10%. In Victoria and Queensland it's 5% when the contract price is $20,000 or more. Check your regulator before you send the contract.
Do I need a written contract for a bathroom renovation?
Usually, yes. NSW requires one for work over $5,000 including GST, Victoria for most work over $10,000, and Queensland for work over $3,300.
Should I quote a bathroom without seeing it?
A photo-based ballpark is fine to see if you're in the same range as the customer's budget. A fixed price should come after a site inspection.
How long should a bathroom quote be valid for?
Many tradies use 30 days. Set a date that matches how quickly your material prices change, and put it on the quote.
The bottom line
A good bathroom quote is a clear scope, not a big number. Inspect properly, break the job into trades, put every line in the right bucket, write down the exclusions, and follow your state's deposit rules. Then follow it up. The tradie who sends the clearest quote first and follows up wins more jobs like this.